Cable Overlays

LV OverlayCS Cable Jointing have been carrying out overlays on the SSE HV and LV Network for more than 7 years. During this time we have overlaid in excess of 40,000m of faulty consac cable.

Each year we have worked for SSEPD Major Projects we have had our workload increased due to our success. Our overlay teams have many years experience and provides solutions to many difficulties that arise due to the nature of this work.

Customer and client liaison is critical to the success of these schemes due to the multiple supply interruptions when swapping properties from the old main to the new.

The jointing required for this type of work is carried out under live conditions to minimise the supply interruption. Overlay work is completed on the public highway within strict time restraints imposed by the local authority.

Our employees hold NRSWA Cards authorising them to work on the highway and we always complete our work within programme.